| S.No. | Head | Cost approved by TAC at 2023 PL (in Rs Cr.) | Appraisal for approval by EFC (in Rs Cr.) | AA & FS against which Expenditure incurred (in Rs Cr.) | Balance Cost (in Rs Cr.) |
|---|---|---|---|---|---|
| I | A- Preliminary | 49.65 | 15.18 | 15.18 | 34.47 |
| II | B-Land | 188.98 | 40.97 | 14.39 | 174.59 |
| III | C- Civil Works | 1336.71 | 1336.71 | ||
| IV | K- Building | 29.94 | 29.94 | ||
| V | M- Plantation | 1.76 | 1.76 | ||
| VII | O- Miscellaneous | 31.84 | 1.35 | 1.35 | 30.49 |
| VI | P- Maintenance during construction @1% of total cost of C- Civil Works & K- Building | 13.67 | 13.67 | ||
| VII | Q- Special T&P | 4.62 | 4.62 | ||
| VIII | R- Communication | 136.47 | 33.14 | 0.95 | 135.52 |
| IX | X- Environment and Ecology | 87.41 | 31.6 | 87.41 | |
| X | Y- Losses on stock @ 0.25% of total cost of C- Civil Works and K- Buildings | 3.42 | 3.42 | ||
| XI | Establishment Cost | 0.84 | 0.84 | ||
| XII | Tools and Plants | 1.00 | 1.00 | ||
| XIII | Suspense | 0.00 | 0.00 | ||
| XIV | Receipt and Recoveries | -1.36 | -1.36 | ||
| XV | Capitalisation of Abatement of Land Revenue | 0.16 | 0.16 | ||
| XVI | Audit and Account Charges | 4.71 | 4.71 | ||
| XVII | 18% GST on C- Civil Works | 240.61 | 240.61 | ||
| Total | 2130.42 | 122.24 | 31.88 | 2098.54 |
| Description | Balance Cost (Crores) | Year I | Year II | Year III | Year IV | Year V | Year VI |
|---|---|---|---|---|---|---|---|
| Construction of Dam/WCS/Appurtenant Work & Consultancy Works and Studies | 2098.54 | 141.75 | 300.00 | 650.00 | 650.00 | 300.00 | 56.79 |
| Cumulative Physical Progress | - | - | 15% | 40% | 65% | 90% | 100% |
| S.No. | Particulars | Amount (in Rs Lakh) | Already Deposited amount (in Rs Lakh) | Balanced amount to be released (in Rs Lakh |
|---|---|---|---|---|
| 1 | Revised NPV | 3174.93 | 1439.42 | 1735.51 |
| 2 | CAT Plan | 7116.60 | - | 7116.60 |
| Total | 10291.53 | - | 8852.11 | |
| S.No. | Particulars | Amount (in Rs Lakh) |
|---|---|---|
| 1 | Compensation for Land | 730.02 |
| 2 | Annuity Amount | 1720.00 |
| 3 | Subsistence grant for displaced families | 27.36 |
| 4 | Provision of transportation for displaced families | 38.00 |
| 5 | Provision of Cattle shed/ Petty shop cost | 7.25 |
| 6 | One time Resettlement allowance | 172.00 |
| 7 | Provision of Stamp duty/ Registration fee/ SLAO Charges etc. | 167.23 |
| 8 | Cost of Affected Houses | 938.16 |
| 9 | Compensation for Fuel/Fodder & Horticultural trees | 69.15 |
| 10 | Interest as per R&R Policy | 350.41 |
| 11 | Compensation to Stake Holders Departments for affected properties | 1103.24 |
| Total | 5322.82 (53.23 cr.) |
|
This sub-head consists of the items like restoration of land in construction areas, removal of trees, control of aquatic weeds in submerged areas, measures to prevent forest fires, public health measures, treatment of the watershed around reservoir rim, catchment area treatment and treatment of degraded/highly degraded lands along the reservoir etc.
| S.No. | Description | Qty | Amount (Rs. Lakh) |
|---|---|---|---|
| 1 | Catchment Area Treatment Plan | Job | 7116.60 |
| 2 | Biodiversity conservation & management plan | Job | 89.40 |
| 3 | Public Health Delivery System | Job | 25.00 |
| 4 | Construction of colony roads, protection wall and boundary wall | Job | 128.71 |
| 5 | Fishery Management Plan | Job | 55.00 |
| 6 | Dumping sites and muck disposal | Job | 449.79 |
| 7 | Solid Waste management | Job | 130.25 |
| 8 | Maintenance of air, water and noise level | Job | 100.00 |
| 9 | Stabilization & Restoration Quarry sites | Job | 171.18 |
| 10 | Provisions for fuel & energy conservation | Job | 50.00 |
| 11 | Disaster & hazard management plan | Job | 125.00 |
| 12 | Environment monitoring plan | Job | 300.00 |
| Total | 8740.93 | ||